RFI, RFQ or RFP: which request should an amenity buyer send?
Send an RFI when you are still learning who can supply you, an RFQ when you know exactly what you want and need prices, and an RFP when you want suppliers to propose how they would meet a need. Using the wrong request wastes time on both sides and produces answers you cannot compare.
By Hemang Jain, Founder, Anadoris
What do RFI, RFQ and RFP mean?
- RFI (request for information): a short questionnaire to learn what suppliers can do. It asks about capabilities, certifications, formats and experience, not prices.
- RFQ (request for quotation): a request for prices on a defined specification and quantity. Every supplier quotes on the same thing.
- RFP (request for proposal): a request for a solution. You describe the outcome, such as a refillable range for a group of hotels, and suppliers propose products, service and price.
In short: an RFI asks who you are, an RFQ asks what it costs, and an RFP asks how you would do it.
Some buyers also use an RFT (request for tender), a formal version of an RFQ or RFP with fixed submission rules, common in public bodies and large groups. The logic is the same: the request should match how much you already know about what you want.
Which request suits which situation?
This table matches each request type to the stage of buying it fits best.
| Request | Use it when | You get back | Main risk |
|---|---|---|---|
| RFI | You are building a longlist or entering a new category | Capability profiles | Answers too general to rank |
| RFQ | The specification is fixed, for example a re-tender of a current range | Comparable prices and terms | Suppliers quote different things if the spec is loose |
| RFP | You want ideas, such as a move to refills or a new brand range | Proposals with products, service and price | Proposals hard to compare side by side |
Many buyers run them in sequence: an RFI to shortlist, then an RFP or RFQ to the shortlist only.

What belongs in an amenity RFI?
Keep it short so good suppliers bother to answer. Ask for:
- Whether the company manufactures, trades or distributes, and where.
- Certified quality systems and the site they cover.
- Product formats and size range available.
- Typical minimum order approach for standard and branded products.
- Export or multi-site experience, in general terms.
- Standard documents available, such as specifications and ingredient lists.
Do not ask for prices in an RFI. Without a fixed specification, any price you receive is a guess.
Ask the same questions of every supplier and in the same order. It makes the answers far quicker to compare, and it signals to suppliers that you are running a fair process. Give a clear reply date and say what happens next, for example that shortlisted suppliers will be invited to quote and send samples.
What makes an RFQ comparable?
An RFQ only works if every supplier prices exactly the same thing. Specify each line item with:
- Product type and fill size.
- Formula requirements, or your approved reference sample.
- Primary pack: bottle material, closure type, decoration.
- Secondary pack: carton or shrink wrap, units per carton.
- Annual quantity and expected order size per call-off.
- Delivery point and Incoterm you want quoted.
- Payment terms you propose.
Ask suppliers to state any assumption they made. An unstated assumption, such as a cheaper closure, is the most common reason two quotes look different.
For a full brief structure, see our RFP template guide; this article covers which request to send, not how to word every clause.
When is an RFP worth the extra effort?
An RFP takes longer to write and longer to evaluate, so save it for decisions with several right answers. Typical cases are moving a group from miniatures to dispensers, launching a branded range, or asking for a supply model across several countries.
Describe the outcome, the constraints and how you will judge proposals. State the weighting in advance, for example quality, service, sustainability and total cost, so suppliers know what matters. Ask each supplier to include a sample set and a named team.
An RFP should also ask how the supplier would manage the change, not only what it would supply. For a dispenser rollout, that means installation support, staff training material and a plan for using up existing stock. For a branded range, it means artwork handling, approval rounds and how the first production run will be checked. These answers often separate suppliers more clearly than the price line does.
Give suppliers a fair window to reply and a named contact for questions. Share every answer to a supplier question with all bidders, so nobody gains an advantage from asking.

How should you compare the replies?
Build a simple comparison grid before replies arrive, so the format of the answers does not steer you. Put requirements in rows and suppliers in columns. Mark each cell as met, partly met or not met, and add notes.
Then normalise prices to the same basis: same quantity, same Incoterm, same currency and the same payment terms. A quote delivered to your door cannot be compared directly with a factory-gate price.
Finally, follow up in writing on anything unclear and keep the replies on file. They become your record of what each supplier promised.
Close the loop with every bidder. Be honest with unsuccessful suppliers. A short note explaining the main reason, such as price, format or service model, keeps the door open for future requests and makes them more willing to put effort into your next one.
If you are preparing a request now, STAY by Anadoris accepts specifications through its quotation form and sets out its buying process on the procurement page.
Questions on this topic
Can I skip the RFI?
Yes, if you already know the suppliers in the category. An RFI is most useful when you are entering a new category or region.
How many suppliers should receive an RFQ?
Enough to give real comparison, but few enough that you can evaluate each reply properly. Many buyers send it only to a short list from an earlier RFI.
Should I share my budget in an RFP?
Sharing a range can help suppliers propose realistic options. Some buyers prefer to withhold it; either way, state the evaluation criteria clearly.
Keep reading
- Manufacturer, trader or distributor: who should supply your amenities?
- Sourcing hotel amenities from India for properties abroad
- How to compare amenity samples from rival suppliers fairly
- How to run a virtual factory audit of an amenity supplier
- How to stock an Airbnb bathroom
- Hospital and clinic bathroom amenities: what to consider
- Gym locker room amenities: a practical checklist
Looking for supply? See Hotels & resorts, browse the product range or request samples.